???? 據2月6日Neftegaz.RU.報道,2020年,巴庫-第比利斯-杰伊漢管道的運營支出約為1.11億美元,資本支出約為2900萬美元。該管道出口了約2.11億桶(超過2780萬噸)的原油。從里海開采的石油通過BTC經由格魯吉亞運送到杰伊漢的海運終端,然后通過油輪從那里運送到全球市場。
????從2006年6月開始運營到2020年底,全長1768公里的BTC管道共輸送原油35.7億桶(超過4.75億噸),這些貨物裝載在4659艘油輪上,并運往世界市場。
????這條管道于2006年7月開通,被稱為“世紀能源項目”,除了從俄羅斯和哈薩克斯坦等該地區其他國家輸送石油外,還從里海輸送阿塞拜疆的石油。
????預計運力為每年5000萬噸石油,即每天100萬桶。Azeri-Chirag-Gunashli油田生產的輕質油也通過BTC運輸。
????BTC管道股東為:BP (30.1%);AzBTC (25%);摩爾(8.9%);挪國油Equinor (8.71%);TPAO(6.53%);埃尼集團(5%);道達爾Total(5%),伊藤忠商事株式會社(3.4%);INPEX(2.5%)、埃克森美孚ExxonMobil(2.5%)和onGC(2.36%)。
????王佳晶 摘譯自 Neftegaz.RU.
????原文如下:
????BP Azerbaijan: Baku-Tbilisi-Ceyhan pipeline exported 27.8 million tons of crude oil in 2020
????Baku-Tbilisi-Ceyhan pipeline spent in 2020 about $111 million in operating expenditure.
????In 2020 Baku-Tbilisi-Ceyhan (BTC) pipeline exported around 211 million barrels (more than 27.8 million tonnes) of crude oil loaded on 278 tankers at Ceyhan.
????The oil extracted from the Caspian Sea is delivered to the marine terminal in Ceyhan via Georgia with the BTC, and from there to global markets via tankers.
????According to BP Azerbaijan, BTC spent in 2020 about $111 million in operating expenditure and about $29 million in capital expenditure.
????Since the 1,768 km BTC pipeline became operational in June 2006 till the end of 2020, it carried a total of 3.57 billion barrels (more than 475 million tonnes) of crude oil loaded on 4 659 tankers and sent to world markets.
????The pipeline, inaugurated in July 2006 and dubbed the "energy project of the century," carries Azerbaijani oil from the Caspian Sea, in addition to volumes from other countries in the region like Russia and Kazakhstan.
????The projected capacity is 50 million tonnes of oil per year or 1 million barrels per day. Light oil produced at the Azeri-Chirag-Gunashli field is transported via BTC.
????The BTC pipeline shareholders are: BP (30.1 %); AzBTC (25 %); MOL (8.9 %); Equinor (8.71 %); TPAO (6.53 %); Eni (5 %); Total (5 %), ITOCHU (3.4 %); INPEX (2.5 %), ExxonMobil (2.5 %) and onGC (2.36 %).